Question 1: Which RMF step is responsible for selecting the initial set of security controls based on the system's impact level?
- Assess
- Select (Correct answer)
- Implement
- Authorize
Correct answer: Select
The Select step involves choosing appropriate security controls from NIST SP 800-53 based on the system categorization and impact level.
Question 2: What document formally records the security controls selected for an information system and their implementation status?
- Plan of Action and Milestones (POA&M)
- System Security Plan (SSP) (Correct answer)
- Security Assessment Report (SAR)
- Authorization to Operate (ATO)
Correct answer: System Security Plan (SSP)
The System Security Plan (SSP) documents the selected controls, their implementation details, and the system's security posture.
Question 3: In the RMF Assess step, who typically conducts the security control assessment?
- The system owner
- An independent assessor or assessment team (Correct answer)
- The authorizing official
- The information system security officer
Correct answer: An independent assessor or assessment team
NIST requires that assessors be independent from the system development team to ensure objectivity and avoid conflicts of interest.
Question 4: What is the primary output of the RMF Assess step?
- Authorization to Operate (ATO)
- Plan of Action and Milestones (POA&M)
- Security Assessment Report (SAR) (Correct answer)
- System Security Plan (SSP)
Correct answer: Security Assessment Report (SAR)
The Security Assessment Report (SAR) documents the findings from the security control assessment, including deficiencies and recommendations.
Question 5: Which NIST publication provides the catalog of security and privacy controls used during the RMF Select step?
- NIST SP 800-37
- NIST SP 800-53 (Correct answer)
- NIST SP 800-30
- FIPS 199
Correct answer: NIST SP 800-53
NIST SP 800-53 provides the comprehensive catalog of security and privacy controls that organizations select from during the RMF Select step.
Question 6: An organization identifies a control deficiency but cannot remediate it before the authorization deadline. What document captures this risk?
- System Security Plan (SSP)
- Security Assessment Report (SAR)
- Plan of Action and Milestones (POA&M) (Correct answer)
- Risk Executive Framework
Correct answer: Plan of Action and Milestones (POA&M)
The Plan of Action and Milestones (POA&M) formally documents known weaknesses, planned remediation actions, and target completion dates.
Question 7: In a federal context, who holds ultimate accountability for accepting the residual risk of operating an information system?
- Information System Security Officer (ISSO)
- System Owner
- Authorizing Official (AO) (Correct answer)
- Chief Information Officer (CIO)
Correct answer: Authorizing Official (AO)
The Authorizing Official (AO) is the senior official accountable for accepting residual risk and granting an Authorization to Operate.