Risk Management in Procurement Flashcards
6 cards from real CPPB practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Risk Management in Procurement flashcards as text
What is the first step in a formal procurement risk management process?
Answer: Identifying potential risks that could affect procurement outcomes
Risk identification—systematically cataloging what could go wrong—must precede any analysis, mitigation planning, or monitoring activities.
In public procurement, which bond guarantees that a contractor will complete a project according to contract terms?
Answer: Performance bond
A performance bond protects the agency by ensuring the surety will complete the work or compensate the agency if the contractor defaults.
Which risk response strategy involves shifting the financial impact of a risk to a third party?
Answer: Transfer
Risk transfer moves the financial consequence of a risk—such as through insurance, bonds, or indemnification clauses—to another party.
A public agency requires a 5% bid bond from all construction bidders. What is the primary purpose of this requirement?
Answer: To discourage low-quality bids and ensure the winning bidder will execute the contract
A bid bond assures the agency that the winning bidder will enter into the contract; if they refuse, the bond compensates the agency for re-solicitation costs.
Which of the following is an example of a 'supply chain risk' in public procurement?
Answer: A geopolitical event disrupting the delivery of critical components
Supply chain risk refers to disruptions—such as natural disasters, geopolitical instability, or logistics failures—that can prevent suppliers from delivering goods or services.
What does a risk register document in a procurement risk management plan?
Answer: Identified risks, their likelihood, impact, owner, and planned response actions
A risk register is the central repository that captures each identified risk along with assessment data and the responsible party's mitigation or contingency plan.