Applied Methods and Techniques Flashcards
7 cards from real CP3P practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Applied Methods and Techniques flashcards as text
When building a Public Sector Comparator (PSC), which element represents the value of risks the government would keep under both traditional procurement and the PPP?
Answer: Retained risk
Retained risk is the risk the procuring authority keeps either way, so it is costed in the PSC and also added to the PPP's cost.
A PSC is adjusted upward to remove advantages a public entity has over a private bidder, such as tax exemptions. What is this adjustment called?
Answer: Competitive neutrality
Competitive neutrality adjustments remove cost advantages that come only from public ownership so the PSC and the bids can be compared fairly.
In a quantitative Value for Money test, the PPP option is preferred when its risk-adjusted net present cost is:
Answer: Lower than the risk-adjusted PSC
VfM is shown when the risk-adjusted present cost of the PPP is below that of the risk-adjusted PSC.
A project team gives each identified risk a probability and a financial impact, then multiplies the two. What does this produce?
Answer: The risk's expected value
Probability multiplied by impact gives the expected value of a risk, which is used to price risk in the PSC.
Which technique runs thousands of simulations with random input values drawn from probability distributions to produce a range of possible project costs?
Answer: Monte Carlo simulation
Monte Carlo simulation samples input distributions repeatedly to generate a probability distribution of outcomes such as P50 or P90 costs.
During appraisal, a team changes one key variable at a time (e.g., construction cost +15%) to see how the result moves. This is called:
Answer: Sensitivity analysis
Sensitivity analysis tests how outputs respond to a change in one variable while all others stay fixed.
Optimism bias adjustments in project appraisal are mainly used to correct for:
Answer: Systematic underestimation of costs and durations
Optimism bias uplifts correct for the well-documented tendency of appraisers to underestimate capital costs, works duration and operating costs.