A data center manager is calculating the facility's Power Usage Effectiveness (PUE).
The total energy consumed by the data center is 500,000 kWh, and the energy consumed by the IT equipment is 350,000 kWh.

What is the PUE, and what does this value indicate?

Select your answer

What Practice Test Geeks adds beyond an AI chat for CDCP

An AI chatbot can quiz you, but it can't reproduce the exam conditions or keep your record. Here you get:

  • A timed, full-length CDCP mock exam — 40 questions in 60 minutes with a 68% pass mark, modeled on the official exam's question count and time limit, followed by a score report broken down by exam domain.
  • A fixed CDCP question bank: the same test every attempt, so your score is comparable from one try to the next instead of changing with every regenerated quiz.
  • Progress saved on your device: completed tests, scores and missed questions stay in My Progress, so you can retake only what you got wrong.
  • A printable CDCP cheat sheet you can print or save as a PDF.
  • CDCP flashcards built from the same question bank.